Article 1 These Measures are formulated in accordance with the Regulations on Power Supply and Use and the relevant provisions of the state, for the purpose of strengthening the administration of permits for undertaking (repairing, testing) electric power facility installation, maintaining the market order of undertaking, repairing, and testing electric power facilities, and regulating the licensing acts for undertaking (repairing, testing) electric power facilities.

Article 2 These Measures apply to the application, acceptance, review, issuance, administration, and supervision of permits for undertaking (repairing, testing) electric power facilities. Where the state has other provisions, those provisions shall prevail.

Article 3 The State Electricity Regulatory Commission shall be responsible for guiding and supervising the issuance and administration of permits for undertaking (repairing, testing) electric power facilities nationwide. The dispatched agencies of the State Electricity Regulatory Commission (hereinafter referred to as the licensing authorities) shall be responsible for the acceptance, review, issuance, and routine supervision and administration of permits for undertaking (repairing, testing) electric power facilities within their respective jurisdictions.

Article 4 Any entity that engages in the business of undertaking, repairing, or testing electric power facilities within the territory of the People's Republic of China shall obtain a permit for undertaking (repairing, testing) electric power facilities in accordance with the provisions of these Measures. No unit or individual may engage in the business of undertaking, repairing, or testing electric power facilities without obtaining a permit for undertaking (repairing, testing) electric power facilities.

For the purpose of these Measures, undertaking, repairing, and testing electric power facilities refer to the installation, maintenance, and testing of electric power facilities for power transmission, power supply, and power reception.

Article 5 Units that have obtained permits for undertaking (repairing, testing) electric power facilities shall carry out business in accordance with the law and be protected by law.

Chapter II Classification and Grading

Article 6 Permits for undertaking (repairing, testing) electric power facilities are divided into three categories: undertaking, repairing, and testing.

Those who obtain a permit for undertaking electric power facilities of the undertaking category may engage in the installation business of electric power facilities.

Those who obtain a permit for repairing electric power facilities of the repairing category may engage in the maintenance business of electric power facilities.

Those who obtain a permit for testing electric power facilities of the testing category may engage in the testing business of electric power facilities.

Article 7 Permits for undertaking (repairing, testing) electric power facilities are divided into five grades: Grade I, Grade II, Grade III, Grade IV, and Grade V.

Those who obtain a Grade I permit for undertaking (repairing, testing) electric power facilities may engage in the installation, maintenance, or testing business of electric power facilities at all voltage levels.

Those who obtain a Grade II permit for undertaking (repairing, testing) electric power facilities may engage in the installation, maintenance, or testing business of electric power facilities at voltage levels below 220 kV.

Those who obtain a Grade III permit for undertaking (repairing, testing) electric power facilities may engage in the installation, maintenance, or testing business of electric power facilities at voltage levels below 110 kV.

Those who obtain a Grade IV permit for undertaking (repairing, testing) electric power facilities may engage in the installation, maintenance, or testing business of electric power facilities at voltage levels below 35 kV.

Those who obtain a Grade V permit for undertaking (repairing, testing) electric power facilities may engage in the installation, maintenance, or testing business of electric power facilities at voltage levels below 10 kV.

Chapter III Application

Article 8 An application for a permit for undertaking (repairing, testing) electric power facilities shall be submitted to the licensing authority at the place where the applicant is located.

A unit that undertakes, repairs, or tests electric power facilities may apply to the administrative department for industry and commerce for a business license or change of business scope only after obtaining a permit for undertaking (repairing, testing) electric power facilities issued by the licensing authority.

Article 9 An application for a permit for undertaking (repairing, testing) electric power facilities shall meet the following conditions:

(1) Having the status of a legal person;

(2) Having a registered capital commensurate with the category and grade of the applied permit;

(3) Having equipment, business premises, and related resources commensurate with the category and grade of the applied permit;

(4) The technical director and safety director shall have technical titles commensurate with the category and grade of the applied permit, and shall not hold concurrent positions in other units;

(5) Having professional personnel commensurate with the category and grade of the applied permit, and they shall not hold concurrent positions in other units.

Applicants for Grade I to Grade III permits for undertaking (repairing, testing) electric power facilities shall also have performance records commensurate with the category and grade of the applied permit within the specified period.

An application for a permit for undertaking (repairing, testing) electric power facilities shall meet the specific conditions specified in the Appendix to these Measures, the Standards for Grades of Permits for Undertaking (Repairing, Testing) Electric Power Facilities.

Article 10 An application for a permit for undertaking (repairing, testing) electric power facilities shall provide the following materials:

(1) A permit application form;

(2) Legal person certification materials and net asset certification materials;

(3) A list of major equipment and machinery, and certification materials for business premises;

(4) Resumes of the technical director and safety director, and relevant certification materials such as professional and technical qualification certificates;

(5) A detailed list of engineering technical personnel and economic management personnel, and their professional and technical qualification certification documents;

(6) A registration form for electric operation personnel.

Applicants for Grade I to Grade III permits for undertaking (repairing, testing) electric power facilities shall also provide performance reports and relevant certification materials for engaging in related business within the specified period.

Article 11 A newly established unit after merger shall re-apply for a permit for undertaking (repairing, testing) electric power facilities to the licensing authority. The grade of the permit for the newly established unit after merger shall be determined according to the conditions actually met, but shall not be higher than the highest grade of the same type of permit among the parties before the merger.

When a newly established unit after merger applies for a permit for undertaking (repairing, testing) electric power facilities, in addition to the materials specified in Article 10, it shall also provide the following materials:

(1) Certification materials for the merger;

(2) The permits for undertaking (repairing, testing) electric power facilities of each unit before the merger.

Article 12 A newly established unit after division shall re-apply for a permit for undertaking (repairing, testing) electric power facilities to the licensing authority. The licensing authority shall, based on assets, personnel, equipment, and other conditions, determine that at most one unit after the division may partially or wholly continue the performance of the unit before the division in engaging in the same type of business.

The grade of the permit for the newly established unit after division shall be determined according to the conditions actually met in accordance with these Measures, but shall not be higher than the grade of the same type of permit of the unit before the division.

When a newly established unit after division applies for a Grade I to Grade III permit for undertaking (repairing, testing) electric power facilities, in addition to the materials specified in Article 10, it shall also provide the following materials:

(1) Certification materials for the division;

(2) Performance certification materials;

(3) The permit for undertaking (repairing, testing) electric power facilities of the original unit.